SOUTHEAST
REGION
Juneau BLM Demolition
In the fall of 2007 Ridge was contracted to demolish four former BLM buildings on Mayflower Island near Juneau, Alaska. The property was being turned over to the United States Coast Guard and therefore all structures including concrete stem walls and footings had to be removed. The site was graded with imported gravel and compacted for future development. RCI removed and disposed of over 750 tons of general debris.
Ketchikan
Firing Range Cleanup

Ridge
performed site restoration for the USCG at the old firing
range in Ketchikan. Tasks included the excavation and removal
of lead contaminated soils, import and placement of backfill,
installation of sediment controls and the construction of
a new parking area. Contaminated soils were loaded into
lined roll off containers and shipped to Oregon via barge.
Sentinal
Island Boathouse Demolition

The
scope of this project involved demolishing a 1940’s
USCG boathouse and marine dock on a small remote island
in South East, Alaska. The crew mobilized by helicopter
and the equipment was brought in by barge. A crane mounted
on the barge and fitted with a clam style bucket was used
to demolish and remove the structures. All debris was then
transported back to the City of Juneau for disposal.
Eldred
Rock Lighthouse Cleanup

A crew
of five workers mobilized to this small island via helicopter.
The main goal for this project was to collect and remove all hazardous
materials. Several fuel lines were discovered and properly
decommissioned, demolished and removed. Asbestos was also
found and all hazardous materials were properly packaged
and removed. All debris was sling loaded with helicopters
to Haines, AK.
Biorka
Island Demolition and Site Work

For
this project a barge was required for mobilization of personnel
and equipment. Upon arrival to the island Ridge’s
tasks included demolition of three FAA housing units, destruction
of several large concrete generator pads, contaminated soil
removal, asbestos abatement, installation of culverts, import
and placement of 260 yards of gravel, and roadway grading.
All debris was transported to Sitka for disposal. The site had a small dock and a bad beach making logistics a challenge.
Level
Island Site Work

Mobilization
was completed with the use of a landing craft and barge.
Because lodging was not available on the island, the crew
was housed in a floating camp transported in from Wrangell.
The job tasks included grading a roadway, culvert installation, asbestos abatement,
remediation of contaminated soil, remodeling of an office
building, and the cutting and removal of several large Sitka
Spruce trees.
Yakutat
Several
FAA facilities were decommissioned and removed. Tasks included
utility disconnect and abandonment, concrete demolition,
backfill grading, and well decommissioning.
|