During the months of August September 2007, RCI mobilized to Dutch Harbor and excavated 3,300 tons of POL contaminated soils. The soil was placed directly into lined containers and barged to Oregon for disposal. The location of the excavation was near the footings of several historic buildings and the contaminated soil could not be immediately transported offsite; so safety, planning and communication were paramount in getting this project completed on time and without incident. All backfill material was blasted locally and transported to the site with 10 yard end dumps.
Cold
Bay Civil Services
Ridge
Contracting has had several projects in this community.
The largest project involved the excavation and remediation
of 15,000 tons of contaminated soil. Other tasks on this
project involved concrete pad demolition, poly-liner debris
cleanup, backfilling, and final grading. Other projects
included demolition of an FAA commissary building, removal
and disposal of several concrete foundations and capped
an old landfill. Equipment for our Cold Bay work has been
found locally and also transported by barge.
Dutch
Harbor (Amakanak Island)

The
scope of this project involved site characterization, smashing
and disposing of old POL drums, setting well head vaults,
installing bollards, removing and reinstalling fence and
finish grading several acres of land for drainage.
Illiamna
Clean Up Project

This
was an environmental waste clean up project for the FAA.
Tasks included asbestos abatement, lead paint removal, general
debris cleanup and decommissioning FAA housing units. Debris
that was not suitable for onsite disposal was consolidated, containerized and loaded onto
a chartered C-130 aircraft and transported to Anchorage for disposal in a DEC permitted landfill.
Dillingham
Tank Pull
Ridge
decommissioned a fuel storage tank at the Dillingham airport
and built a long term stock pile for the contaminated soil.
Later that year Ridge also flew into the nearby village
of Portage Creek and excavated a fuel oil spill. Lodging
for the crew was in tents. Local equipment was available
on site to complete the project.
Sparrevohn
Clean Up Contract
This
was an FAA Radome recovery / cleanup project. A Radome was
ripped from its foundation during a wind storm. Pieces of
debris were scattered for miles. This limited access job
was completed with the help of all terrain vehicles and
a helicopter. Ridge’s crew had to fight the brush
and bugs in order to gather large pieces of debris. The
debris was sling loaded to the nearby landing strip where
it was then transported by chartered aircraft to Anchorage
for disposal.
Other Projects in this area include:
-Bethel, Sand Point, Kodiak and more Cold Bay (UST removal and cutting).
- Amaknak FAA infrastructure demolition and King Salmon test pitting.
|